File #: 19-755    Version: 1 Name:
Type: Action Report Status: Reported to Board
File created: 8/23/2019 In control: Parks and Environment Committee
On agenda: 9/4/2019 Final action: 9/4/2019
Title: Elk/Beaver Lake Remediation Project - Progress Update
Attachments: 1. Staff Report: Elk/Beaver Lake Remediation Prjct-Progress Update, 2. Appendix A: Proposed Work Plan and Schedule, 3. Appendix B: Business Case for In-Lake Remediation at Elk/Beaver

Title

Elk/Beaver Lake Remediation Project - Progress Update

 

Recommendation

That the Parks & Environment Committee recommend to the Capital Regional District Board:

1. That this report be received for information;

2. That staff be directed to pursue external funding opportunities and partnerships to offset costs associated with the remediation of Elk and Beaver lakes; and

3. That staff incorporate capital and operating expenditures into the Regional Parks five-year financial plan, subject to receiving at least 50% capital grant funds for the project.

(WA)