Title
The Summit at Quadra Village Project Main Works Packages
Award of Contracts CRHD.2017-12-015 through CRHD.2017-19-022 inclusive
Recommendations
a) That Contract CRHD.2017-12-015-Glazing for the Summit at Quadra Village Project be awarded to Pino-Lite Glass (2010) Ltd. in the amount of $2,540,242 [excluding GST] and that a project contingency of $76,207 [excluding GST] be approved.
b) That Contract CRHD.2017-13-016-Doors, Frames, Hardware for the Summit at Quadra Village Project be awarded to McGregor & Thompson Hardware Ltd. in the amount of $1,223,975 [excluding GST] and that a project contingency of $36,719 [excluding GST] be approved.
c) That Contract CRHD.2017-14-017-Ceramic Tile for the Summit at Quadra Village Project be awarded to Hourigan's Flooring in the amount of $43,800 [excluding GST] and that a project contingency of $1,314 [excluding GST] be approved.
d) That Contract CRHD.2017-15-018-Acoustical Ceilings for the Summit at Quadra Village Project be awarded to Talcore Walls & Ceilings Ltd. in the amount of $543,750 [excluding GST] and that a project contingency of $16,313 [excluding GST] be approved.
e) That Contract CRHD.2017-16-019-Resilient Flooring for the Summit at Quadra Village Project be awarded to Hourigan's Flooring in the amount of $1,099,640 [excluding GST] and that a project contingency of $32,989 [excluding GST] be approved.
f) That Contract CRHD.2017-17-020-Seamless Epoxy Flooring for the Summit at Quadra Village Project be awarded to RADA Resurfacing in the amount of $358,290 [excluding GST] and that a project contingency of $10,749 [excluding GST] be approved.
g) That Contract CRHD.2017-18-021-Painting for the Summit at Quadra Village Project be awarded to M & L Painting Ltd. in the amount of $640,750 [excluding GST] and that a project contingency of $19,223 [excluding GST] be approved.
h) That Contract CRHD.2017-19-022-Patient Lifts for the Summit at Quadra Village Project be awarded to Guldmann Care-Lift Solutions ULC in th...
Click here for full text