Skip to main content
File #: 25-1093    Version: 1 Name:
Type: Action Report Status: Carried
File created: 10/6/2025 In control: Capital Regional District Board
On agenda: 10/8/2025 Final action: 10/8/2025
Title: Arena Accessibility Improvement Project Revised Scope Proposal
Attachments: 1. Staff Report: Arena Accessibility Improvement Project

Title

Arena Accessibility Improvement Project Revised Scope Proposal

 

Recommendation

[At the October 2, 2025 meeting of the Peninsula Recreation Commission, the recommendation to Board (part 2 in report) was amended and carried as follows:]

That the Peninsula Recreation Commission recommends to the Capital Regional District Board:

That the five-year capital plan be amended to update the project costs and that the arena capital plan in 2027 be debt financed up to 7.1 million and that the detailed design work commence as soon as possible.