File #: 22-445    Version: 1 Name:
Type: Action Report Status: Reported to Board
File created: 6/29/2022 In control: Electoral Areas Committee
On agenda: 7/13/2022 Final action: 7/13/2022
Title: Upgrade of Cooling System for the Salt Spring Island Public Library
Attachments: 1. Staff Report: Upgrade of Cooling System SSI Library

Title

Upgrade of Cooling System for the Salt Spring Island Public Library

 

Recommendation

The Electoral Areas Committee recommends the Capital Regional District Board:
That the Salt Spring Island Library Service 2022 Capital Plan to be amended to increase the Cooling System Upgrade Project budget from $102,500 to $195,150. The additional budget of $92,650 is to be funded from Community Work Fund ($60,000) and the service Capital Reserve Fund ($32,650).  
(WA)